The construction site is currently covering all the areas available on the East side

The coverage of all the available areas on the East side has been completed, following the installation of Pier 10 towards via Perlasca. This enabled PERGENOVA to move ahead with the construction work for the new bridge. Meanwhile, the installations of the foundation piles for Piers 9 and 11 are proceeding, simultaneously with the activities of wartime munition reclamation and those related to the resolution of the interferences, already started in the past few weeks.