The construction site is fully active on the west side

PERGENOVA is systematically carrying on its weekly activities, with the aim of proceeding with the work while guaranteeing the maximum quality of both the work and of the design and construction process. 

  
On the west side, the preparatory work for the construction of the foundation piles for Pier 2 has just started, alongside with those for Pier 3 and the operations for the construction of the foundation plinth for Pier 5.

Simultaneously, the activities for the construction of the plinth for Pier 9 are being started.
Therefore, the work for the foundations for six out of nine Pier - which will sustain the bridge on the west side - are currently being made.

On the east side, the wartime munition reclamation activities continue.

 