Genoa -

The construction works for the foundation poles of three piles are proceeding simultaneously

This week in the construction site - thanks to the simultaneous activity of three drilling rigs - the foundation poles of three piles are being built: to the east for pile number 10 and to the west for piles number 4 and 3, whose works will begin following the end of the construction site set-up activities.
On both sides, the work for the plinths construction is proceeding: on the east one for the start of that concerning pile number 1; on the west one, for the continuation of the work for the plinth concerning pile number 9 and for the start of the works on that of pile number 5.