The construction site is currently covering all the areas available on the East side

The coverage of all the available areas on the East side has been completed, following the installation of the pile number 10 towards via Perlasca. This enabled PERGENOVA to move ahead with the construction works for the new bridge. Meanwhile, the installations of the foundation poles for piles number 9 and 11 are going forward, simultaneously with the activities of wartime munition reclamation and those related to the resolution of the interferences, already started in the past few weeks.